IMACS progress report no. 59

 

B. Bigelow                        20 March 2003

 

I)    Project Status

 

Currently scheduled tasks:                    Status:

 

a)    DSS drive assembly/testing (Hare, Kowal)        Done

b)    DSS drive test/integration (Birk)            IP

c)    Calibration sys. drafting (Cleary)            Done

d)    Calibration sys. fab (Kowal)                IP

e)    CCD array testing (Thompson/Burley)            IP

f)    Dewar/Detector final integration (Thompson/Burley)    IP

g)    Grism procurement (Sutin)                IP

h)    Instrument electronics assembly (Bagish)        on sched.

i)    Control software design (Birk)                on sched.

j)    Short Camera opto-assembly (Bigelow)            Done

k)    IFU design and build (U. Durham)            IP

 

Project events in February:

 

 - First light with short camera!

 - Thermal testing delayed until final assembly complete

 - Thermal testing enclosure test assembly completed

 - IMACS pre-ship review delayed, currently unscheduled

 - Magellan engineering time set aside for IMACS install - August '03

 - Magellan FC/ACD optics delayed until September

 

Latest project images:

 

Final Assy:        http://obs.carnegiescience.edu/instrumentation/imacs/devel/final/index.html

Enclosures:       http://obs.carnegiescience.edu/instrumentation/imacs/devel/enclosures/index.html

Disperser Server:  http://obs.carnegiescience.edu/instrumentation/imacs/devel/dss/index.html

Filter Servers:       http://obs.carnegiescience.edu/instrumentation/imacs/devel/fss/index.html

 

II)    Optics (Sutin)

 

 - Echellette prism due from Zygo 5/7/03

 - Investigating calibration lamp types

 - Started daily status report page (http://obs.carnegiescience.edu/~sutin/imacs/status.txt)

 - Continued on-going flexure and optical testing

 

III)    Electronics (Bagish)

 

 - 3 power supply chassis assembled (guiders, array controllers)

 - Need slide assembly for PS chassis to mount in racks

 - L05 motor controller chassis finished and installed

 - RS-422 communications chassis designed, panels in engraving

 - Assembly of ABS box for PI controller in progress

 - Cables ready for new IGUS chain

 - Temp and pressure sensors ready for mounting

 

IV)    Software (Birk/Clardy)

 

Birk:

 

 - Misc. motion control testing continues

 - Problem identified with shutter motors - bad cable?

 - Filter server testing finished except for discrete filter locations

 

Clardy:  

 

 - Improved optical modeling code - good to a pixel now.

 - Created test files to continue mask cutter commissioning

 - LDSS2 mask made with laser

 - Design of IMACS mask making GUI due by 5/1/03

 

V)    Detector Systems (Thomson/Burley)

 

 - Working on CCD readout problems, bleeding

 - Temp circuits added to pre-amp boards for additional temp sensors

 - PCI and DSP PCB revisions in progress

 - Working on temperature control code for CCDs

 

VI)    Mechanics (Bigelow/Hare)

 

Bigelow:

 

In February:

 

1) Finished short camera assembly and installed on instrument

2) Tested long camera focus motors with new PI controllers (w/ Birk)

3) Ordered all cooling system parts, started assembly of cooling system

4) Additional parts for new IGUS wrap and utility wrap designed, ordered

5) New getters designed, drafted, and fabricated for dewar

6) First grism cell fully assembled

7) Revised filter server insertion mechanisms completed and installed

 

In March:

 

1) Continue plumbing installation

2) Install second IGUS chain, re-route plumbing and cabling

3) Install first grism, both imaging mirrors on DSS

4) Continue final spacing measurements on collimator focus, cameras, dewar, BFD

5) Design shutter motor guards

6) Continue flexure testing

7) Re-mount S04 in new cell (from M&T)

8)

 

Hare:

 

 - Continue assembly, testing, and rework of all guide cameras as necessary.

 - Assembly and testing of Disperser Server System, including drive and

   cable wrap sub-assemblies.

 - Designed baffles for filter insertion stages

 - Re-design center field guider stage to rotate barrel assemblies

 

VII)    Fabrication (Kowal)

 

February's Report:

 

1) Finished machining components for all grating tilt mechanisms.

2) Made three getter assemblies.

3) New filter server arm & key made, plus additional modifications to FSS.

4) Various Dewar parts were made or modified.

5) Modified instrument rollers.

6) New parts for filter server made: spacers and top plates.

7) Cooling panels made.

8) Worked on disperser carousel, including: new limits switches, modifying

   IGUS chains & correcting M & T manufacturing error on carousel.

 

Expectations for March:

 

1) Six grating cells complete.

2) Delrin filter server guides.

3) Parts for second imaging mirror support.

4) Calibration lamp reflector block.

5) Short camera barrel spacer.

6) Programming of cable tray parts.

 

 

IX)     Other Business

 

Next meeting:  10:15 AM, 4/2/03

 

 

 

 

 

 